• HVAC calibration
 • P&ID loop verification
 • HEPA filter integrity test data review
 • Critical equipment calibration status
 • Site Acceptance Tests(SATs)
 • Installation Qualification tests
 • Piping and welding documentation
 • Utility verification
 • System standard operating procedures and work instructions 
 The output of this phase should be an IQ report addressing all the above elements, and an SDL file that documents the following elements: 
• Project changes
 • IQ tests performed
 • Calibration
 • Supplier supplied documents
 • Equipment certificate
 • Installation deviations
 • Site Acceptance Tests (SAT)
 • Consumable list
 • Spare part list
 • Environmental review report
 • List of Operational and Instructional documents 
 IQ approval is a pre-requisite for the start of the Operational Qualification (OQ) phase.


 
                